Gas Production Halved in a Decade, SSGC Chief RevealsPakistan
Pakistan’s local gas production has fallen by almost half over the past ten years, the managing director of Sui Southern Gas Company has said, as households receive piped gas only during three daily cooking windows this winter.

SSGC Managing Director Muhammad Amin Rajput told local media in an interview that the country’s domestic gas production had dropped by about half in a decade, according to Azaad Urdu. He said the decline in local output was the main reason households were now receiving gas only at limited hours.
He said the gas available to SSGC had fallen to about 605 million cubic feet per day, compared with 695 million cubic feet per day last year, because of the depletion of gas wells. Of this, about 300 million cubic feet per day is being supplied to domestic consumers, while the rest goes to industry, power plants and the fertiliser sector.
In view of the situation, the company has prepared a schedule to supply gas to domestic consumers only during breakfast, lunch and dinner hours, so that every household gets fuel when it is needed most. The company has been reviewing gas availability continuously over the past week, he said.
The winter schedule was announced on November 4, 2026. Under it, SSGC and Sui Northern Gas Pipelines Limited (SNGPL) supply gas to domestic consumers in three fixed slots a day: 6:30am to 9:00am, 12:00pm to 2:30pm and 6:00pm to 9:00pm, giving homes about eight hours of gas daily around cooking times.
SSGC supplies Sindh and Balochistan, while SNGPL serves Islamabad, Punjab and Khyber Pakhtunkhwa. Both utilities said the timings follow federal government directions to prioritise domestic consumers during cooking hours. For SSGC areas, the new schedule is a cut from last season, when the morning slot ran from 6:30am to 10:00am.
The shortage is driven by falling local production and difficulties in securing imported liquefied natural gas (LNG), which normally fills part of the gap left by declining domestic gasfields. QatarEnergy has extended its force majeure on LNG supplies to Pakistan until December 29, and the government has been planning about ten cargoes for December and January against an estimated requirement of twenty.
Petroleum Minister Ali Pervaiz Malik has said domestic demand is expected to rise by 400 to 500 million cubic feet per day in winter. On the SNGPL network alone, winter demand is expected to rise from about 550 million cubic feet per day to about 1,100 million cubic feet per day, according to Petroleum Division plan figures.
SNGPL has also cut gas supply to the compressed natural gas (CNG) sector from 50 million cubic feet per day to 35 million cubic feet per day, with plans to suspend CNG supplies altogether in the coming days, as the utilities prioritise household consumption while supplies remain tight.
Consumers have also complained of low gas pressure even within the scheduled supply windows. According to the SSGC administration, the biggest cause of low pressure is the use of illegal compressors and suction pumps by consumers, which pull gas from the whole block or building. These devices are not only illegal but also dangerous, and have often caused damage to property and sometimes loss of life, the administration said.
With local reserves depleting and imported LNG supplies constrained, the authorities say careful management of the limited gas available and its fair distribution have become unavoidable. Neither company has announced an end date for the three-window schedule, and the Petroleum Division’s winter load management plan covers November 2026 to February 2027.