SHC Halts Nehr-i-Khayyam Construction in KarachiPakistan
The court suspended work on the disputed Clifton project and adjourned the case to 18 January 2027, as petitioners warn the canal’s drainage role is at risk.

The Sindh High Court has ordered an immediate halt to disputed construction and development work along Nehr-i-Khayyam in Karachi’s Clifton area, after petitions challenged the project over the alleged commercial use of public amenity land and stormwater drainage areas.
The court directed that the work be suspended while the petitions are heard, and adjourned the proceedings until 18 January 2027. The order does not decide the merits of the case, which remain to be argued before the court.
What the petitioners allege
The petitions were filed by Jamaat-e-Islami and residents of Clifton, including Advocate Saifuddin, the Leader of the Opposition in the City Council, and three other petitioners. They have named the chief secretary, the local government secretary, the Karachi Metropolitan Corporation, the Karachi Development Authority, the Karachi Water and Sewerage Corporation, the Sindh Environmental Protection Agency and the Boat Basin station house officer as respondents.
According to the petitioners, construction and development have been carried out in and around Nehr-i-Khayyam and adjoining amenity plots, raising questions about the preservation of the natural waterway and the possible commercial use of land linked to it. They contend that the work has proceeded without a proper technical and environmental assessment, and that it could affect the flow of rainwater during the monsoon.
Residents say the channel is an essential stormwater drain for the surrounding neighbourhoods, and they fear that concrete structures and any narrowing of the waterway could restrict rainwater and tidal flows, increasing the risk of urban flooding during heavy rain. Rasha Tariq, of the Clifton Residents Committee, has said workers were continuing construction around the clock, and has claimed that three drains built along the canal could worsen flooding.
Jamaat-e-Islami Karachi Deputy Chief Saifuddin Advocate has said the government sought an environmental impact assessment only after residents protested, and has argued that it should have been completed before the project was approved and construction began.
The petitioners have asked the court to declare the alleged conversion of the stormwater drain into a recreational park or commercial venture illegal, and to preserve Nehr-i-Khayyam for its lawful purpose as a stormwater drainage channel. They have also sought the removal of structures, encroachments and other works already carried out within the lawful boundaries of the channel.
In their petition, they have also referred to earlier judgements of the Supreme Court and the Sindh High Court, contending that the judiciary had stopped construction in the vicinity of Nehr-i-Khayyam on a number of occasions, but that work resumed after reported suspensions lasting only a brief period.
Construction on the project was reportedly nearly 80 per cent complete when the legal challenge was mounted, a figure that has added to residents’ concern that much of the work could be finished before the courts reach a final decision. The court’s interim order now puts that work on hold until the next hearing.
For now, the dispute remains before the court. The petitioners’ claims about the legality of the project, the adequacy of its environmental assessment and the risk to drainage have yet to be tested in full, and the authorities named in the petitions will have the opportunity to present their position when the case is taken up again on 18 January 2027.